Lampiran
2 |
: |
SE-17/PJ.6/2003 |
Tanggal |
: |
23
Mei 2003 |
PETUNJUK TEKNIS PENILAIAN BANGUNAN OBJEK KHUSUS
ANALISA PERHITUNGAN BIAYA PEMBUATAN BARU (CRN)
DERMAGA/PELABUHAN
- |
ANALISIS HARGA SATUAN/M2 BREASTING/MORRING
DOLPHIN |
- |
ANALISIS HARGA SATUAN/M2 JETTY/DERMAGA |
- |
ANALISIS HARGA SATUAN/M2 |
Jakarta 2003
DEPARTEMEN KEUANGAN REPUBLIK
DIREKTORAT JENDERAL PAJAK
DIREKTORAT PBB DAN BPHTB
DERMAGA
JETTY
ANALISIS
HARGA SATUAN PER M2
JENIS PEKERJAAN |
SAT |
VOL |
BAHAN (Rp) |
UPAH (Rp) |
JUMLAH (Rp) |
HARGA (Rp) |
||
A. |
PERSIAPAN |
|
|
|
|
|
|
|
|
1 |
Pengukuran |
m' |
1,00 |
7.220 |
3.187 |
10.407 |
10.407 |
|
2 |
Mobilisasi
peralatan |
|
1,00 |
ls |
|
- |
20.000 |
B |
KONSTRUKSI
UTAMA |
|
|
|
|
|
|
|
|
4 |
Pemancangan |
m' |
2,50 |
52.000 |
20.800 |
72.800 |
182.000 |
|
5 |
Pemotongan
Tiang |
bh |
|
0,20 |
15.600 |
15.600 |
3.120 |
|
6 |
Bekisting |
m2 |
0,34 |
119.000 |
153.821 |
272.821 |
92.759 |
|
7 |
Pembesian |
m3 |
0,34 |
490.500 |
210.460 |
700.960 |
238.326 |
|
8 |
Pengecoran |
m3 |
0,34 |
337.450 |
192.509 |
529.959 |
180.186 |
|
9 |
Floorhard |
m2 |
1,00 |
5.000 |
1.500 |
6.500 |
6.500 |
C |
FINISHING |
|
|
|
|
|
|
|
|
10 |
Lapisan
penetrasi |
m2 |
1,00 |
15.135 |
6.886 |
22.021 |
22.021 |
|
11 |
Lapisan
aspal |
m2 |
1,00 |
|
|
20.435 |
20.435 |
CRN |
Rp/m2 |
|
|
|
|
826.155 |
||
D |
ASESORIS |
|
|
|
|
|
|
|
|
12 |
Bolard |
unit |
0,10 |
|
|
360.000 |
36.000 |
|
13 |
Fender |
unit |
0,08 |
|
|
180.000 |
14.400 |
DERMAGA
ANALISIS
HARGA SATUAN PER M2
JENIS PEKERJAAN |
SAT |
VOL |
BAHAN (Rp) |
UPAH (Rp) |
JUMLAH (Rp) |
HARGA (Rp) |
||
A. |
PERSIAPAN |
|
|
|
|
|
|
|
|
1 |
Pengukuran |
m' |
1,00 |
7.220 |
3.187 |
10.407 |
10.407 |
|
2 |
Mobilisasi
peralatan |
ls |
1,00 |
|
- |
20.000 |
|
B |
KONSTRUKSI
UTAMA |
|
|
|
|
|
|
|
|
4 |
Pemancangan |
m' |
2,00 |
52.000 |
20.800 |
72.800 |
145.000 |
|
5 |
Pemotongan
Tiang |
bh |
|
0,20 |
15.600 |
15.600 |
3.120 |
|
6 |
Bekisting |
m2 |
0,34 |
119.000 |
153.821 |
272.821 |
92.759 |
|
7 |
Pembesian |
m3 |
0,34 |
490.500 |
210.460 |
700.960 |
238.326 |
|
8 |
Pengecoran |
m3 |
0,34 |
337.450 |
192.509 |
529.959 |
180.186 |
|
9 |
Floorhard |
m2 |
1,00 |
5.000 |
1.500 |
6.500 |
6.500 |
C |
FINISHING |
|
|
|
|
|
|
|
|
10 |
Lapisan
penetrasi |
m2 |
1,00 |
15.135 |
6.886 |
22.021 |
22.021 |
|
11 |
Lapisan
aspal |
m2 |
1,00 |
|
|
20.435 |
20.435 |
CRN |
Rp/m2 |
|
|
|
|
739.355 |
DERMAGA
BREASTING/MORRING
DOLPHIN
ANALISIS
HARGA SATUAN PER M2
JENIS PEKERJAAN |
SAT |
VOL |
BAHAN (Rp) |
UPAH (Rp) |
JUMLAH (Rp) |
HARGA (Rp) |
||
A. |
PERSIAPAN |
|
|
|
|
|
|
|
|
1 |
Pengukuran |
m' |
1,00 |
7.220 |
3.187 |
10.407 |
10.407 |
|
2 |
Mobilisasi
peralatan |
ls |
1,00 |
|
|
- |
20.000 |
B |
KONSTRUKSI
UTAMA |
|
|
|
|
|
|
|
|
4 |
Pemancangan |
m' |
0,30 |
52.000 |
20.800 |
72.800 |
21.840 |
|
5 |
Pemotongan
Tiang |
bh |
0,10 |
|
15.600 |
15.600 |
1.560 |
|
6 |
Bekisting |
m2 |
0,32 |
119.000 |
153.821 |
272.821 |
87.303 |
|
7 |
Pembesian |
m3 |
0,32 |
490.500 |
210.460 |
700.960 |
224.307 |
|
8 |
Pengecoran |
m3 |
0,32 |
337.450 |
192.509 |
529.959 |
169.587 |
|
9 |
Floorhard
|
m2 |
1,00 |
5.000 |
1.500 |
6.500 |
6.500 |
C |
FINISHING |
|
|
|
|
|
|
|
|
10 |
Lapisan
penetrasi |
m2 |
1,00 |
15.135 |
6.886 |
22.021 |
22.021 |
|
11 |
Lapisan
aspal |
m2 |
1,00 |
|
|
20.435 |
20.435 |
D |
ASESORIS |
|
|
|
|
|
|
|
|
12 |
Bolard |
unit |
0,05 |
|
|
360.000 |
18.000 |
|
13 |
Fender |
unit |
0,01 |
|
|
180.000 |
1.800 |
CRN |
Rp/m2 |
|
|
|
|
603.760 |